Typical Assembly Process for a 150m2 house
Day 1-5
assembly of closed panel timber frame superstructure commences
and erected to fully weather proofed building
Day 5-7
Roof covering, fascia and scoffed installed
Week 2
External finishes complete i.e. render stone, timber cladding
Week 2-10
Internal finishes first and second fix mechanical electrical
installations
Week 11
Quality control for professional finish undertaken
Week 12-14
Your ÖkoHaus home ready for occupation

|